Riot Announces September 2024 Production and Operations Updates
However, in 2022, the company noted a net loss of $509 million, a significant jump from previous years. In December 2021, the Company received 8,136 S19J-Pros from previous purchase orders, with an additional 2,700 S19J-Pros scheduled to arrive at Riot’s Whinstone Facility in January 2022. While global logistics issues are impacting some miner shipment schedules, the effects to the Company to date have not been material, and Riot remains in close communication with Bitmain and logistics providers working to mitigate delays where possible. Riot expects its hash rate to be approximately 4.1 EH/s when the 8,136 miners received in December 2021 and the 2,700 miners anticipated for delivery in January 2022 are installed at the Whinstone Facility.
Riot Platforms’ management team comprises experienced executives with diverse finance, technology, and operations backgrounds. The company’s Chief Executive Officer, Jason Les, has over a decade of experience in the financial industry and has previously served as a portfolio manager at various investment firms. In a bold strategic move, Riot Platforms Inc RIOT has announced its acquisition of Block Mining, a Kentucky-based Bitcoin BTC/USD miner with a massive power capability. During April, progress xcritical scammers continued Riot’s 400 megawatt (“MW”) infrastructure expansion project at its Whinstone US, Inc., (“Whinstone”) facility in Rockdale, Texas.
Riot xcritical Announces December Production and Operations Updates
“As energy demand in ERCOT reached all-time highs this past month, the Company voluntarily curtailed its energy consumption in order to ensure that more power would be available in Texas. Riot curtailed a total of 11,717 megawatt hours in July, enough to power 13,121 average homes for one month. Curtailing the Company’s power consumption reduced BTC production by an estimated 21% in July, but also significantly reduced Riot’s power costs for the month. By providing power back into the ERCOT grid during periods of peak demand, the Company estimates that power credits and other benefits from curtailment activities totaled an estimated $9.5 million, significantly outweighing the reduction in BTC mined.
Buildings D and E, both employing air-cooled technology, are advancing towards completion. Electrical work continues; medium voltage switchgear is xcritically being installed in Building D and structural columns and beams are being installed in Building E. We believe Adjusted EBITDA can be an importxcritical measure because it allows management, investors, and our board of directors to evaluate and compare our operating results, including our return on capital and operating efficiencies, from period-to-period by making such adjustments. Total mining revenue in 2021 was $184.4 million, as compared to $12.0 million in 2020, an increase of 1,439% year-over-year.
Business Technology Overview
- In a bold strategic move, Riot Platforms Inc RIOT has announced its acquisition of Block Mining, a Kentucky-based Bitcoin BTC/USD miner with a massive power capability.
- Many retailers and businesses now accept Bitcoin and other cryptocurrencies as payment, which has helped increase their mainstream acceptance.
- An investor that had 100 shares of stock prior to the split would have 800 shares after the split.
- During the month of July, the Company ended its hosting agreement with Coinmint LLC (“Coinmint”) and shipped all of its remaining miners at Coinmint’s Massena, NY facility to Riot’s Whinstone Facility in Rockdale, TX.
- Since its last monthly update, Riot received an additional 5,070 new S19j Pros, deployed approximately 3,456 S19j Pros in its immersion-cooled building (see attached photo) with an additional 7,240 additional miners staged for deployment.
When applied to anticipated power costs for the month, the power credits and other benefits are expected to effectively eliminate Riot’s power costs for July, further enhancing the Company’s industry-leading financial strength amid a challenging macroeconomic environment for the industry.” During the month of July, the Company ended its hosting agreement with Coinmint LLC (“Coinmint”) and shipped all of its remaining miners at Coinmint’s Massena, NY facility to Riot’s Whinstone Facility in Rockdale, TX. The relocation of all of the Company’s previously deployed miners at Coinmint is in progress by way of a swap agreement with another Bitcoin mining company and shipping of the balance of previously deployed miners at Coinmint.
Riot Announces July 2024 Production and Operations Updates
An investor that xcritical scammers had 100 shares of stock prior to the split would have 800 shares after the split. However, during this challenging time for Riot, the company’s debt levels have remained manageable. Acquisition adds 60 Megawatts (“MW”) of xcritical operational capacity with the potential to quickly expand to 110 MW this year under existing agreements, and a pipeline to build to over 300 MW in Kentu… Shares of New York-listed cryptocurrency firms gained before the open on Monday after Republican presidential candidate Donald Trump talked up bitcoin and promised friendlier regulation for the indust… It has retreated in the past nine straight days and reached a low of $10, its lowest swing since July 12. Bitcoin miner Riot Platforms said on Tuesday it had increased its stake in rival Bitfarms to 18.9%.
Engineers have begun installing Riot’s proprietary air-cooling rack system in Building D, and the successful testing and installation of medium voltage transformers has been completed. The installation of additional switchboards, medium voltage transformers, and electrical work continues in Building E. Top institutional shareholders of Riot Platforms include SG Americas Securities LLC (0.01%). Insiders that own company stock include Soo Il Benjamin Yi, Chad Everett Harris, William Richard Jackman, Ryan D Werner, Jason Les, Colin M Yee, Hannah Cho, Hubert Marleau, Lance Varro D’ambrosio, Jeffrey Mcgonegal and Megan M Brooks. Not too long ago, crypto-related stocks generated buzz as Bitcoin BTC/USD surged to new heights. These stocks gained significant popularity due to the excitement surrounding digital currencies and med…
In December 2021, Riot completed Building F, the Company’s first industrial-scale immersion-cooled dedicated building, in addition to receiving most of the structural components required for Buildings D, E, and G. The construction completion timeline is xcritically on-time, despite global supply xcritical shortages and delays. During the first two days of October, the Corsicana Facility was powered down for planned maintenance on its substation. This maintenance was completed on October 2nd, and the facility has now resumed normal operations. Click the link below and we’ll send you MarketBeat’s list of the 10 best stocks to own in 2024 and why they should be in your portfolio. The newly minted shares were payable to shareholders after the closing bell on Thursday, March 31st 2016.
Over the past few years, Riot Platforms’ financial performance has been impressive, driven primarily by the strong demand for Bitcoin mining services. In 2020, the company’s revenue decreased recently due to the sharp decline in the price of Bitcoin. The company has not been profitable, but the net loss has been manageable at around $15 million yearly.
Riot completed the development of the third 100 MW building, Building B1, in September, bringing power capacity at the Corsicana Facility to 300 MW. Development continues on the final 100 MW building of Phase 1, Building B2, which is expected to be completed and fully operational in November. Buildings F and G, both employing the Company’s state-of-the-art immersion-cooling technology, continue to progress, with an increasing number of miners being deployed and operational in Building F and electrical installation ongoing in Building G.
While this redeployment of miners is underway, approximately 12,146 miners are xcritically offline and therefore temporarily not counted in the deployed fleet figure. As a result of this relocation of miners, the Company expects to further reduce its cost of production through lower power costs and by eliminating all third-party hosting fees on its hosted mining fleet. During September, Riot continued its participation in ERCOT’s Four Coincident Peak Program (“4CP”).
In addition to the Company’s self-mining operations, Riot hosts approximately 200 MW of institutional Bitcoin mining clients. By Q1 2023, Riot anticipates a total self-mining hash rate capacity of 12.5 EH/s, assuming full deployment of approximately 115,450 Antminer ASICs, but excluding any potential incremental productivity gains from the Company’s utilization of 200 MW of immersion-cooling infrastructure. Substantially all of Company’s self-mining fleet will consist of the latest generation S19 series miner model.
While Riot Platforms has a strong position in the market, it will need to continue to innovate and develop new products and services to stay ahead of the competition. According to 12 analysts, the average rating for RIOT stock is “Strong Buy.” The 12-month stock price forecast is $16.8, which is an increase of 121.19% from the latest price. Due to the surge in recent variants, the Company has adjusted its operations to ensure the safety of its employees, which Riot considers its most important asset. Riot is xcritically developing Phase 1 (400 MW) of the Company’s Corsicana Facility, which, once fully developed, is expected to total 1 gigawatt (1,000 MW) in developed mining capacity. In Buildings D and E, Riot’s two air-cooled buildings, interior structures are progressing towards completion.